LEPOA POINT PARK BULKHEAD
SEPTEMBER 15, 2008 – HURRICANE IKE
FEB 2011 – BULKHEAD REPAIRS TO POINT PARK LED BY DENNIS RAYMOND $2,545
MAY 26, 2012 – DISCUSSED AT BOARD MEETING
APRIL 27, 2013 – ANNUAL MEETING – VOTED UNANIMOUSLY (38‐0) FOR SPECIAL ASSESSMENT TO FUND FUTURE EXPENSE; ASSUMING 300’ @ $200/FT $60,000; OWNERS TO BE ASSESSED $200 PER YEAR OVER A 5 YR PERIOD
DEC 7, 2013 – BOARD MEETING: 100’ BULKHEAD CLOSEST TO BURKE HAS STARTED TO FAIL DUE TO SEVERE STORMS AND SUSPECTED TIE‐BACK FAILURE
SURVEY OF POINT PARK IS OBTAINED AND ACTUAL WATERFRONTAGE IS APPROX 400’
APRIL 26, 2014 – ANNUAL MEETING DISCUSSED POSSIBILITY OF ACCELERATING REMAINING BULKHEAD ASSESSMENT; ASSUMED 1 YEAR LIFE ON BULKHEAD
APRIL 25, 2015 – ANNUAL MEETING DISCUSSED BULKHEAD REPAIRS; APPROVED $2,500 FOR REPAIRS
MAY 2015 – BULKHEAD REPAIRS PERFORMED WITH VOLUNTEERS HEADED BY PAUL RILEY; SECTION CLOSEST TO BURKE WAS TOO SEVERE TO REPAIR
APRIL 16, 2016 ‐ – ANNUAL MEETING BOARD IS GIVEN DISCRETION TO REPAIR OR REPLACE BULKHEAD BASED ON FUNDS AVAILABLE; OWNERS ENCOURAGED TO PAY 2016 AND 2017 ASAP
AUGUST 1, 2016 – SIGNED CONTRACT WITH IVY CONSTRUCTION $76,600 (408’@$190/FT) NOT INCLUDING BACKFILL
SEPTEMBER 21, 2016 – AFTER PERMITTING DELAYS CONSTRUCTION BEGINS
NOVEMBER 9, 2016 – BULKHEAD COMPLETED AND BACKFILL/DIRT WORK BEGINS; A‐1 DIRT $2,640 (IVY PROVIDED MACHINERY)
DECEMBER 2, 2016 – CONSTRUCTION COMPLETED
MARCH 27, 2017 – WORKDAY AT POINT PARK TO FINISH DIRT WORK